A
B
Shaking table is holding up over the supports (About 2.5 meters over the
floor level)
Gradual movement towards north in the velocity of 1.8 meters per minute
C
D
Gradual movement towards east in the velocity of 3.0 meters per minute
Lowering into the pit in the velocity of 0.3 meters per minute
E
F
G
Shaking table fixed in the pit
EShaking table weight is 775 ton:Installing with two cranes each with
400 ton
EShaking table was moving into the pit from 15:00 to 17:30
@AB Moving towards north; 1.8 meters per minute in about 10
minutes
@CD Moving towards east; 3.0 meters per minute in about 10
minutes
@EFG Installation in the pit; 0.3 meters per minute in about 30
minutes
Shaking table installation(May 19, 2004)
The shaking table weighted 775 ton (798 ton if the weight of cables is
included) was hold up with two cranes each with 400 ton capacity, and installed
in the pit on May 19,2004.