INDEX
- October 8, 2007 Specimens after removal from Shaking Table
- October 7, 2007 Clearance of ALC Panels
- October 5, 2007 Clearance of Interior Walls and Ceilings
- October 3, 2007 Breaking up of the Specimen
- September 27, 2007 Collapse Test
- September 25, 2007 Open Experiment at E-Defense
- September 20, 2007 Shaking Table Test began at E-Defense.
- September 12, 2007 The construction of the specimen was completed!
- September 10, 2007 The specimen was moved to the shaking table.
- September 8, 2007 The specimen was ready for moving to the shaking table.
- September 7, 2007 The shaking table was ready for setting the specimen.
- August 31, 2007 Outside scaffolding was taken down.
- August 30, 2007 Operations on the shaking table began.
- August 28, 2007 Ineterior Finsh Work was completed.
- August 22, 2007 Lightgage Steel for Hanging Ceiling was set up
- August 21, 2007 The Installation of the Partion Walls began.
- August 10, 2007 Installation of Aluminum Sashes
- August 8, 2007
The assembly of steel frames for hanging the specimen
- August 4, 2007 Installation of Exterior Walls (ALC Panels)
- August 2, 2007 Fire Resistive Covering ( Calcium Silicate Board)
- August 1, 2007 Fire Resistive Covering ( Sprayed Rock Wool )
- July 28, 2007 Skeleton Work was completed.
- July 25, 2007 Strain Gauges were Pasted.
- July 21, 2007 Floor Slab Concrete was Placed.
- July 18, 2007 Steel Bar Arrangement was completed.
- July 13, 2007 Wire Mesh was Spread.
- July 12, 2007 Welding of Stud Connector was Completed.
- July 11, 2007 The Long-term Vibration Monitoring was started.
- July 10, 2007 Outside scaffolding was put up.
- July 09, 2007 Final tightening was completed.
- July 05, 2007 The Erection of the Steel Frames was completed.
- July 04, 2007 The Anti-Collapse Frames were installed.
- July 03, 2007 The Anti-Collapse Frame was assembled.
- July 02, 2007 The Erection of the Steel Frames began at E-Defense
- June 26, 2007 The Steel Frames are ready for E-Defense