- November 4, 2008 Concrete foundations were installed.
- November 6, 2008 Installation of steel foundations.
- November 11, 2008 Election of steel foundations were completed.
- November 13, 2008 Election of the steel frames (1).
- November 14, 2008 Election of the steel frames (2).
- November 17, 2008 Election of the steel frames (3).
- November 18, 2008 Marking and final tightning of H.T.B.
- November 18, 2008 Election of the steel frames were completed.
- November 26, 2008 Outside scaffoldings were completed.
- November 27, 2008 Installation of roof floor deck.
- December 1, 2008 Steel bar arrangement of the 2nd floor.
- December 3, 2008 The 5th floor slab concrete was placed.
- December 8, 2008 Steel bar arrangement of the 2nd floor concrete weights were completed.
- December 9, 2008 Shackle and wire for the suspension of the specimen.
- December 11, 2008 Concrete of the 2nd floor weights were placed.
- December 19, 2008 ALC panels were installed.
- December 19, 2008 Concrete weights of 4th floor.
- December 19, 2008 Connection of columns and girders.
- December 21, 2008 ALC window frames are placed.
- December 22, 2008 Curtain wall frames are placed.
- December 23, 2008 LGS for dry patition wall is placed.
- January 6, 2009 Doors are placed.
- January 7, 2009 Appearance of specimen.
- January 8, 2009 Appearances of Stairs.
- January 20, 2009 Steel dampers are placed.
- January 20, 2009 Frame for measurement are placed.
- January 23, 2009 Specimen moved into the Experiment Building.
- February 12, 2009 Specimen moved on the Shaking Table.
- March 8, 2009 Steel dampers are replaced by Viscous dampers.